Lower Vasse River Management - Improving Water Quality

The Lower Vasse River is a stretch of the Vasse River approximately 5.5km in length, runs from the Vasse Diversion Drain to the estuary, and flows through the centre of Busselton. This section is greatly modified, with a significant portion of catchment flows diverted to Geographe Bay (to protect against residential flooding) and was historically impounded by a weir structure downstream at the Old Butter Factory. The river is highly eutrophic (impacted by excess nutrient loads), with cyanobacterial blooms occurring each year during the warmer months. The river receives excess nutrients from the urban and rural catchment inflows, from groundwater, and potentially from river sediment. Isolation of flow, poor water quality, and location have led to the need for specific management of this waterbody. 

Updates

28 November 2024

The City of Busselton is continuing with its commitment to improving the health of the Lower Vasse River through the assessment of a new aeration trial.

The City’s Waterways Management Committee was established in 2024 and its members have been reviewing the outcomes of previous dredging work and other approaches to reduce algal blooms that occur each summer in the river, which are caused by excess nutrients from the urban and rural catchment.

Whilst the long term solution to prevent these nutrients from entering the local waterways, a range of approaches have been undertaken by the City and its partner agencies to look at ways to reduce algal blooms in the interim.

The State Government is the owner of the river, but in recent years the City has agreed to take on the role of Interim Asset Manager to enable a more responsive approach to ensuring its health. Investigating an aeration trial is the next step in our ongoing work to care for the river on behalf of the community.

Stage 3 of the City’s sediment removal program is currently in the procurement phase and still requires environmental approvals. The assessment of the aeration trial will be progressed through the Vasse Taskforce Water Quality Decision Support Framework and will require endorsement through the Vasse Ministerial Taskforce.

30 September 2024

Native fringing (riparian) vegetation of the Lower Vasse River has been largely cleared, leaving a narrow strip of remnant trees. The City of Busselton is working towards re-establishing this vegetation, and earlier this year a group of dedicate staff banded together and plant over 260 native seedlings along a section of the Lower Vasse River bank. After some well overdue rain in the past months, it’s great to see these plants thriving.

 Vegetation along the river provides important habitat for terrestrial fauna, with overhanging trees offering many roosting and nesting sites for waterbirds. In addition to providing habitat benefits, fringing vegetation is a vital component of river health. The important functions include: - supporting terrestrial and aquatic food webs; - habitat for terrestrial and aquatic fauna; - foreshore stabilisation; - maintaining cooler temperatures - interception of nutrients and sediments in runoff; and - nutrient uptake and processing.

The planting day was coordinated by the City’s Green Taskforce, a group of staff who collectively work towards raising staff awareness and encourage more sustainable behaviours in the workplace by running and supporting sustainability activities and initiatives.

Plants growing along riverbank    Plants growing in the riverbed

11 June 2024

A group of City staff volunteered to spend some time planting 260 plants along the banks of the Vasse River last week. The plants were a mixture of locally native species common in areas along riverbanks, this included specifies suited for right on the water’s edge, to those that grow further out.

The plants will help provide important foraging and breeding habitat for native animals, increase connectivity of habitat by providing corridors for animals and areas that foster improved biodiversity and ecological function. In addition, the plants will improve bank stabilisation and reduce nutrients entering the river, provide shade to improve riverbank conditions and water quality, and improve resilience to climate change.  

Planting in riverside areas along the Lower Vasse River also aligns with strategies and actions in the Lower Vasse River Waterway Management Plan developed by the Department of Water and Environmental Regulation, City of Busselton and the Vasse Taskforce.

People planting trees   Person planting plant near river   Man sitting next to plant by the river

1 May 2024

The City of Busselton has completed a trial pit of approximately 4 tonnes of sediment testing on a section of the lower Vasse River. The purpose of the trial was to see how the material behaves when excavated/handled and will also undergo various tests including ASS (Acid Sulphate Soils) and water content. As this was a trial, there were no requirements to get any specific additional approvals. The material will be transported to the City’s transfer facility and will be further inspected and treated for ASS.

April 2024

The City of Busselton continues to work through its 6 staged-approach of sediment removal, established in 2022, with locations for each stage chosen based on water quality and priority.

The completion of the Stage 2 sediment removal in June 2023 saw approximately 670t of dry sediment removed. This sediment was laid to semi-dry in collection bags before being laid out on an Acid Sulphate Soils (AA) treatment pad at the Busselton Waste Transfer Station to treat and neutralise it. The City was then able to repurpose the sediment as daily cover at the Dunsborough Waste Facility.

The Department of Water and Environment Regulation (DWER) continue to monitor the water in the river to ensure effectiveness of the current sediment removal program. It was found during Stages 1 and 2 that pH levels and the clarity of the water were kept within acceptable ranges throughout the works. This data assists City and DWER officers with ongoing evaluation of the program.

In April 2024 the City advertised a tender for Stage 3 of the sediment removal process and this tender will close on 8 May. Stage 3 will focus  on the part of the river near Strelly Street to upstream of the river bend (see map). The total budget for Stage 3 is $938,025, with $407,964 funded by the State NRM Community Stewardship Program.

In addition to sediment removal works, DWER have conducted a large-scale application of a phosphorus-binding clay (Phoslock) from the Causeway bridge downstream to the pedestrian bridge. The results from this, plus the results from Stage 2 of sediment removal, will be presented to Council by DWER in June 2024.

The City of Busselton has also collaborated with DWER to develop a Water Treatment Assessment Framework ensuring decision-making on the management of the waterways (Lower Vasse River and Toby Inlet) is scientifically robust and evidence-based.

Work continues on waterway management and further updates will be provided when available.

 

Removal of Sediment

Map showing the stages of sedimental removal for the lower vasse river

A layer of nutrient-rich, fine organic sediment has accumulated throughout the lower reach of the river. This sediment provides a significant potential internal source of nutrients that may contribute to microalgal growth. Conditions such as low dissolved oxygen and resuspension of sediments caused by physical disturbance, could release nutrients into the water column, feeding microalgae. These soft organic sediments also provide a poor substrate for beneficial aquatic plants, and poor habitat for benthic invertebrates.

The Sediment Removal Project is aimed at removing nutrient rich organic sediments that have accumulated in the river, which impact amenity, water quality, and benthic habitat. While sediment removal alone is not expected to prevent microalgal blooms occurring in the river, it has been identified as a step to reducing the extent, severity and duration of blooms in the future.

The project is a key recommendation from the Lower Vasse River Waterway Management Plan (City of Busselton, 2019) and benefits from community support.

Due to the large volumes of sediments, a staged approach is necessary to minimise environmental impacts and also due to logistical and financial constraints.  Sediment removal staging was prioritised on a values basis as opposed to in a linear fashion, with locations for the initial stages of sediment removal selected based on several factors, including severity of annual algal blooms, level of public access, and technical advice and information available at the time. Availability of suitable land for the laydown area and dewatering process was also considered.

Stages 1 and 2 sediment removal are complete

Stage 1 consisted of dredging along a 200m stretch of the river between the Causeway Bridge and pedestrian bridge adjacent Rotary Park. Dredging was completed from 28 April to 8 June 2022, with the dredge operational for a total of 28 days.

Stage 2 consisted of dredging of sediment along a 300m stretch between the Causeway Bridge and old boat ramp along Southern Drive. Dredging was completed from 2 May to 20 June 2023, with the dredge operational for a total of 30 days.

Water quality testing was undertaken for the duration of the dredging and return water discharge. Results of the testing indicated that while the return water had elevated concentrations of nutrients, this did not result in a toxic algal bloom, the elevated nutrient concentrations did not extend far downstream, and dissipated quickly following completion of return water discharge.

The program has been successful in removing a significant sediment load, approximately 630t and 700t (dry weight) respectively from the first two stages, and the following nutrient load:

Project Stage

Nutrient

Average total nutrient removed (t)

Stage 1

1,638t

Total nitrogen

11.8

Total phosphorus

2.7

Stage 2

1,484t

Total nitrogen

9.0

Total phosphorus

1.2

 

Following the completion of these two stages, the City received analysis from the Department of Water and Environmental Regulation (DWER) who advised that a considerable concentration of nutrients re-entered the river via dewater.

High nutrient concentration in dewater was a risk that was identified during program inception. In an attempt to mitigate this risk, in Stage 1, Phoslock® (a phosphorus-binding clay) was applied to return water prior to re-entry to the river. Phoslock® has successfully been used worldwide to reduce bioavailable phosphorus in aquatic environments.

Unfortunately due to the complex composition of the sediment, Phoslock® was not effective in sufficiently treating the return water. In Stage 2, DWER led a trial that filtered dewater through an off-river treatment system containing Poseidon Pellets, beads that are designed to bind bioavailable phosphorus. A triple filtration system using this product was successful in treating a subset of dewater during the trial. However, to scale-up this method to treat all dewater was found to be prohibitively expensive and the concentration of dissolved aluminium in water after treatment was found to be unacceptably high.

Stage 3 sediment removal

Stage 3 works are scheduled for 2025. The City has been successful in securing $407,964 of funding from the State Natural Resource Management's Community Stewardship Grant Program. Funds will assist with Stage 3 sediment removal works in the Lower Vasse River in a section upstream of the Strelly Street Bridge (Stage 3).

The first two stages were successful in removing considerable sediment and nutrient loads. However, the high concentrations of nutrients that were delivered back to the river via return water during dewatering does not align with the project objectives. The undesirable volume of nutrients returned to the river via dewater and concerns over whether the current method removes an adequate portion of sediment from the riverbed, has led the City to investigate and prioritise alternative methods for Stage 3, such as, in situ dewatering and direct excavation, which has necessitated rescheduling of sediment removal to occur in summer/autumn instead of winter, and additionally amendment of approvals and management plans.

 

Alternative Sediment Removal Method

In April 2024, the City conducted a sediment excavation and pliability trial. The trial showed that while the surface of the exposed sediment appeared dry, sediment remained saturated. The sediment however, was spadeable, and able to be transported off-site and treated, indicating that in situ dewatering and direct excavation may be suitable for this site. The City has undertaken a sediment removal procurement process that requested tenders for both the dredging method and alternatives such as in situ dewatering coupled with direct excavation.

The City is currently procuring project management services and a geotechnical assessment for the stretch of the LVR between Strelly Street and Fairlawn Road (stages 3 and 4). The geotechnical assessment will help to refine the excavation methodology and minimise risk. The City has appointed an environmental consultant for the Stage 3 works, including amendment of current approvals, and discussions with regulators. The environmental contractor will also liaise with the City and stakeholders to refine the in situ dewatering and excavation method to mitigate environmental risks, conduct baseline and ongoing testing and develop/amend all required plans and procedures.

 

In Situ Dewatering and Direct Excavation Methodology

The direct excavation method proposes to undertake the works in a ‘dry’ riverbed over summer and autumn, employing in situ dewatering for inundated areas. Dewatered sediment will be excavated with a 13-tonne excavator and loaded into 9 tonne mini dumper trucks. To enable movement along the riverbed the contractor proposes to construct longitudinal paths and transverse bunds using crushed limestone or marine sandbags. Excavation using a long-reach excavator may also be used. Excavated sediment will be delivered to a limestone pad adjacent to the river, and transported off site daily to the Dunsborough Waste Facility where it will be treated with sand and lime for ASS.

Sediment removal for environmental outcomes is uncommon in natural waterways, and the City is unaware of local instances using in situ dewatering and direct excavation for the purpose of water quality improvements. This method development necessitates a degree of ongoing research and development throughout the works, with a need to be adaptable and innovative.

Environmental parameters and water quality will be monitored throughout the works by an environmental consultant, who will provide management plans, baseline analysis, through to water quality monitoring, sediment disposal requirements, and closure and evaluation reporting.

The City believes that, while in situ dewatering and direct excavation will initially add significant complication and potentially project delays, that it represents the best available solution, and could in time (once the new method has been established and refined) be more financially viable, time efficient and remove a greater proportion of both sediment and nutrient loads from the river.

Future Stages

The City is currently committed to the Sediment Removal Program as a means to improve water quality in the Lower Vasse River. Where practical, and as opportunities arise, more funding applications will be made to support continued sediment removal in the River. However, following completion of the first three stages the City has committed to detailed analysis of program outcomes, before progressing future stages.

Image: Laydown area showing dewatering geotextile bags (Stage 2) – Rotary Park

Project Timeline

February 2021 - Lower Vasse River Management Advisory Group selects sediment removal as the highest priority recommendation for implementation

September 2021 - City was awarded $350,000 under the Healthy Estuaries WA program

February 2022 - Environmental and Heritage approvals granted

Stage 1

April to June 2022 - Stage 1 Dredging works (downstream from Causeway Road bridge)

June-October 2022 - Sediment slurry dewatering in Rotary Park

November 2022 - City was awarded $407,964 under the State NRM Community Stewardship Program for Stage 3 of sediment removal

November 2022-February 2023 - Dewatered sediments transported off site and treated for Acid Sulphate Soils, prior to reuse

Stage 2

May-June 2023 - Stage 2 Dredging works (upstream of the Causeway Road Bridge)

June-October 2023 - Sediment slurry dewatering in Rotary Park

November 2023-February 2024 - Dewatered sediments transported off site, treated for Acid Sulphate Soils, and repurposed as landfill daily cover

Stage 3

Spring/summer 2023 - Carter’s Freshwater Mussel management

Summer/autumn 2025 - Stage 3 of sediment removal (upstream of the Strelly Street Bridge) to commence

Autumn/winter 2025 – Excavated sediment transported off site, treated for Acid Sulphate Soils, and repurposed as landfill daily cover

 

FAQs

Lower Vasse River Sediment Removal FAQs

Related Information

EPBC Compliance Report 2023-2024 - Lower Vasse River

Sediment Disposal and Reuse Options Assessment

Environmental Management Plan for Carter's Freshwater Mussel Westralunio Carteri

Survey of Carter's Freshwater Mussel in the Lower Vasse River

Lower Vasse River - Dredge and Disposal Management Plan

Lower Vasse River - Acid Sulfate Soil and Dewatering Management Plan

Acid Sulfate Soil and Dewatering Management Plan

 

If you've encountered a problem with the website or have any general feedback, please provide comment via this form.

Was this page helpful?

Get Audio Code