Lower Vasse River Management - Improving Water Quality
Updates
30 September 2024
Native fringing (riparian) vegetation of the Lower Vasse River has been largely cleared, leaving a narrow strip of remnant trees. The City of Busselton is working towards re-establishing this vegetation, and earlier this year a group of dedicate staff banded together and plant over 260 native seedlings along a section of the Lower Vasse River bank. After some well overdue rain in the past months, it’s great to see these plants thriving.
Vegetation along the river provides important habitat for terrestrial fauna, with overhanging trees offering many roosting and nesting sites for waterbirds. In addition to providing habitat benefits, fringing vegetation is a vital component of river health. The important functions include: - supporting terrestrial and aquatic food webs; - habitat for terrestrial and aquatic fauna; - foreshore stabilisation; - maintaining cooler temperatures - interception of nutrients and sediments in runoff; and - nutrient uptake and processing.
The planting day was coordinated by the City’s Green Taskforce, a group of staff who collectively work towards raising staff awareness and encourage more sustainable behaviours in the workplace by running and supporting sustainability activities and initiatives.
11 June 2024
A group of City staff volunteered to spend some time planting 260 plants along the banks of the Vasse River last week. The plants were a mixture of locally native species common in areas along riverbanks, this included specifies suited for right on the water’s edge, to those that grow further out.
The plants will help provide important foraging and breeding habitat for native animals, increase connectivity of habitat by providing corridors for animals and areas that foster improved biodiversity and ecological function. In addition, the plants will improve bank stabilisation and reduce nutrients entering the river, provide shade to improve riverbank conditions and water quality, and improve resilience to climate change.
Planting in riverside areas along the Lower Vasse River also aligns with strategies and actions in the Lower Vasse River Waterway Management Plan developed by the Department of Water and Environmental Regulation, City of Busselton and the Vasse Taskforce.
1 May 2024
The City of Busselton has completed a trial pit of approximately 4 tonnes of sediment testing on a section of the lower Vasse River. The purpose of the trial was to see how the material behaves when excavated/handled and will also undergo various tests including ASS (Acid Sulphate Soils) and water content. As this was a trial, there were no requirements to get any specific additional approvals. The material will be transported to the City’s transfer facility and will be further inspected and treated for ASS.
April 2024
The City of Busselton continues to work through its 6 staged-approach of sediment removal, established in 2022, with locations for each stage chosen based on water quality and priority.
The completion of the Stage 2 sediment removal in June 2023 saw approximately 670t of dry sediment removed. This sediment was laid to semi-dry in collection bags before being laid out on an Acid Sulphate Soils (AA) treatment pad at the Busselton Waste Transfer Station to treat and neutralise it. The City was then able to repurpose the sediment as daily cover at the Dunsborough Waste Facility.
The Department of Water and Environment Regulation (DWER) continue to monitor the water in the river to ensure effectiveness of the current sediment removal program. It was found during Stages 1 and 2 that pH levels and the clarity of the water were kept within acceptable ranges throughout the works. This data assists City and DWER officers with ongoing evaluation of the program.
In April 2024 the City advertised a tender for Stage 3 of the sediment removal process and this tender will close on 8 May. Stage 3 will focus on the part of the river near Strelly Street to upstream of the river bend (see map). The total budget for Stage 3 is $938,025, with $407,964 funded by the State NRM Community Stewardship Program.
In addition to sediment removal works, DWER have conducted a large-scale application of a phosphorus-binding clay (Phoslock) from the Causeway bridge downstream to the pedestrian bridge. The results from this, plus the results from Stage 2 of sediment removal, will be presented to Council by DWER in June 2024.
The City of Busselton has also collaborated with DWER to develop a Water Treatment Assessment Framework ensuring decision-making on the management of the waterways (Lower Vasse River and Toby Inlet) is scientifically robust and evidence-based.
Work continues on waterway management and further updates will be provided when available.
Removal of Sediment
This project is part of a multi-staged approach to reducing nutrients and improving health of the Lower Vasse River. The City aims to improve water quality of the River by progressing with staged removal of sediment.
Nutrient-rich sediments have accumulated on the bed of the Lower Vasse River over many decades and are an important factor fuelling the cycle of summertime algal blooms.
While sediment removal alone is not expected to prevent algal blooms occurring in the River, it is an important step if we are to achieve the aim of significantly reducing the extent, severity and duration of blooms in the future.
Sediment removal in the Lower Vasse River is being implemented in a staged approach, targeting a priority stretch of the river at each stage. Where each stage takes approximately 12 months to complete.
Stage 1 sediment removal is complete
Stage 1 dredging was completed in May 2022 with approximately 630 tonnes of sediment (dry weight) removed over the course of seven weeks.
The area dredged, spanned from the Causeway Road Bridge to upstream from the pedestrian bridge on Peel Terrace.
The sediment slurry was pumped into porous geotextile bags, which retained the fine sediments while water was expelled and returned to the River.
The sediments continued to dewater for an additional 6 months. The dewatered sediments were transported off site and treated for acid sulphate soil. Sediment composition limits options for reuse, currently sediments are able to be reused as daily landfill cover, however additional options are being investigated for future stages.
Water quality in the River was closely monitored for the duration of the works to ensure no detrimental impacts from the dredging operation and the dewatering of the sediments.
Stage 2 sediment removal
Stage 2 is well underway, sediments were dredged from May to June 2023 from the section of river, Causeway Road to Old Boat Ramp.
This stage used the same techniques and dewatering area (Rotary Park) as Stage 1, enabling both, refinements in methodology, and cost savings by eliminating the need to establish a new laydown and dewatering area.
It is estimated that 670 tonnes (dry weight) of sediments were removed during Stage 2. These sediments are dewatering in Rotary Park, and will be removed ahead of the War Memorial works due to start in December 2023. Sediments will be transported off-site, treated with lime for ASS (Acid Sulphate Soils) and utilised as daily landfill cover at the Dunsborough Waste Facility.
The Playground in Rotary Park will be closed for the duration of the dredging and dewatering operations for safety reasons.
As in Stage 1, water quality in the River was closely monitored for the duration of the works to ensure no detrimental impacts from the dredging operation and the dewatering of the sediments.
Stage 3 sediment removal
Stage 3 is tentatively scheduled for 2024. The City has been successful in securing $407,964 in funding from the State Natural Resource Management's Community Stewardship Grant Program. Funds will assist with Stage 3 sediment removal works in the Lower Vasse River in a section upstream of the Strelly Street Bridge (Stage 3).
Future Stages
The City is committed to the Sediment Removal Program as a means to improve water quality in the Lower Vasse River. Where practical, and as opportunities arise, more funding applications will be made to support continued sediment removal in the River.
Image: Laydown area showing dewatering geotextile bags (Stage 2) – Rotary Park
Project Timeline
February 2021 - Lower Vasse River Management Advisory Group selects sediment removal as the highest priority recommendation for implementation
September 2021 - City was awarded $350,000 under the Healthy Estuaries WA program
February 2022 - Environmental and Heritage approvals granted
Stage 1
April to June 2022 - Stage 1 Dredging works (downstream from Causeway Road bridge)
June-October 2022 - Sediment slurry dewatering in Rotary Park
November 2022 - City was awarded $407,964 under the State NRM Community Stewardship Program for Stage 3 of sediment removal
November 2022-February 2023 - Dewatered sediments transported off site and treated for Acid Sulphate Soils, prior to reuse
Stage 2
May-June 2023 - Stage 2 Dredging works (upstream of the Causeway Road Bridge)
June-October 2023 - Sediment slurry dewatering in Rotary Park
November 2023-February 2024 - Dewatered sediments transported off site, treated for Acid Sulphate Soils, and repurposed as landfill daily cover
Stage 3
Spring 2023 - Carter’s Freshwater Mussel survey and relocation
Autumn/winter 2024 - Stage 3 of sediment removal (upstream of the Strelly Street Bridge) to commence
FAQs
Lower Vasse River Sediment Removal FAQs
Related Information
EPBC Compliance Report 2023-2024 - Lower Vasse River
Sediment Disposal and Reuse Options Assessment
Environmental Management Plan for Carter's Freshwater Mussel Westralunio Carteri
Survey of Carter's Freshwater Mussel in the Lower Vasse River
Lower Vasse River - Dredge and Disposal Management Plan
Lower Vasse River - Acid Sulfate Soil and Dewatering Management Plan
Acid Sulfate Soil and Dewatering Management Plan